Eastern Pkwy Project

Project Updates: 
Phase 2A - mid-October 2017 through April 2018
September 21, 2017

Replacing a main installed between 1920-1930 is no easy task. But thanks to advances in technology, Louisville Water devised a plan to significantly minimize environmental impacts and neighborhood disruptions, while increasing the lifespan of this critical main.

The project, covering 6.4 miles,  will be completed in phases over the course of three years. Phase 2A, slated for mid-October 2017 through April 2018, involves work on 1.7 miles of the water main along Eastern Parkway from Crittenden Drive at I-65 to Beargrass Creek near Poplar Level Road. The work requires some road and lane closures but customers will continue to have a reliable water source throughout the duration of the project. Check the website often for updates regarding closures and detours.  

We've created a page to answer the most frequently asked questions, but feel free to contact us for additional information. 

 